How to view the Factory Calendar in SAP – Jan 2011 SAP Training Batch

Today one of the SAP Training students asked how to view Factory Calendar in SAP when discussing Scheduling in SAP ?

Use the following Menu path

[ spro -> IMG -> SAP Netweaver -> General Settings -> Maintain Factory Calendar ]

Select “Factory Calendar”  and then click the view button. Select the SAP factory calendar you wanted to view ( in this case “US Factory Calendar” ) and then click on the Definition button.

Here you can see the definition of the US Factory Calendar.

The holidays associated with that calendar can be viewed using the SAP Holiday Calendar ID “US” . As usual , you need SAP Access to practice this. This is important for SAP MM Training, SAP PP Training and other SAP Modules as well.

Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020

Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?

Question 3 : Make the working days in the calendar Zx as Monday through Saturday.

 

Advertisements

7 thoughts on “How to view the Factory Calendar in SAP – Jan 2011 SAP Training Batch

  1. shambhavi gupta says:

    Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020
    A. Calendar ZR created.
    Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?
    A. No.
    Question 3 : Make the working days in the calendar Zx as Monday through Saturday.
    A. Done.

    Like

  2. Vikas says:

    Answers:

    Question 1 : Create a Custom Factory Calendar Zx valid from 2000 to 2020
    Ans. Created VR

    Question 2 : Can you create a Factory Calendar without specifying the Holiday Calendar ?
    Ans.No

    Question 3 : Make the working days in the calendar Zx as Monday through Saturday.
    Ans: Done

    Like

  3. Brian Cooper says:

    How does the Factory Calendar advance each month (using a monthly bucket for planning)…is this automatic or is there a “calendar roll” process? For instance, at the end of June (bucket # 18 in our system), how does the system move bucket#18 to the end of the planning horizn and relable it as the future bucket (i.e,, June 2016)?

    Like

  4. 商務 says:

    We stumbled over here by a different website and thought I may as well check things
    out. I like what I see so now i’m following you.
    Look forward to exploring your web page yet again.

    Like

  5. Best Irons says:

    Wonderful items from you, man. I’ve bear in mind your
    stuff previous to and you are simply extremely excellent.

    I actually like what you’ve obtained here, really like
    what you are saying and the best way wherein you say it.
    You’re making it entertaining and you continue to care for to keep it
    wise. I can’t wait to learn far more from you.

    This is really a tremendous web site.

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s